Recall the First Principles of Corporate Financial Decisions:
Invest in projects that yield a return greater than the minimum acceptable hurdle rate.
Choose a financing mix that minimizes the hurdle rate and matches the assets being financed.
If there are not enough investments that earn the hurdle rate, return the cash to stockholders.
Consider actual cash flows.Consider timing effectively.
Consider risk.
Be adaptive to different situations.
Be understandable to non-financial types.
If the expected cash flows are all the same, then PB = Initial Cost / CF
Example (Project 1 on the handout): PB = 2000/330 = 6.06 Years
If the cash flows are not all the same, you simply sum the cashflows
until the total exceeds the cost of the project. You can use interpolation
to narrow the result down to the desired level of accuracy.
Problems with Payback Period:
DPB is very similar to PB except that it uses discounted cash flows instead of non-discounted cashflows. The advantages of DPB over PB are:
However, it still may suffer the problems of an arbitrary cutoff point
and failure to consider cash flows past the cutoff point.
This class of tools includes similar measures with names like Accounting Rate of Return, Book Rate of Return, Return on Book Value, etc. Do not confuse this with the Internal Rate of Return (IRR).
The example uses a very simple definition: Avg ROI = Avg CF / Cost
NPV is the strongest method for estimating the value of an investment.
It effectively incorporates timing and risk, if properly used. Most important,
it provides an estimate of the value created or destroyed by engaging in
an investment project.
NPV > 0 indicates that value will be created.
NPV < 0 indicates that value will be destroyed.
Profitability Index allows the comparison of projects with different costs by showing the Net Present Value per dollar of invested capital.
PI is computed one of two ways:
NPV ÷ Project Cost
Present Value of Future Cash Flows ÷ Project Cost
Both provide the same information, but the first method gives a PI greater than zero for positive NPV projects and the second method gives a PI greater than one for positive NPV projects. The decimal portion of both gives the NPV generated per dollar of investment.
While PI helps in the ranking of projects, it cannot be used in isolation.
In the presence of a capital constraint, the objective is always to maximize
the total NPV of invested capital.
EAA allows the comparison of projects with different expected life spans by providing a measure of the NPV generated per year of a project's life.
The computation of EAA is simply to determine the equal annual payment (annuity) that would have the same present value as the NPV of the project.
For example, consider Project 7 on the handout. It has a 5 year life
and an estimated NPV of $165. Its EAA is computed as follows:
PV | -165 |
FV | 0 |
n | 5 |
i? | 10 |
PMT? | 43.53 |
The EAA lets us think of this project as generating $43.53 of NPV per
year rather than thinking of it as generating a one-time NPV of $165.
This project can be compared with others with different life spans on this
basis.
The IRR represents the average annual expected rate of return on a project.
IRR is defined as the discount rate that makes NPV = 0.
An NPV profile is
a graph that relates the NPV of a project to changes in the discount rate.
The point at which the NPV profile crosses the horizontal (discount rate)
axis gives the IRR of the project.
Advantages of IRR:
If the project only has one expected inflow and one outflow as in Project
3, the calculation is simply as follows:
PV | -2000 |
FV | 10000 |
n | 15 |
i? | 11.33% |
PMT | 0 |
If the project has equal annual cash flows as in Project 5, the calculation
is:
PV | -2000 |
FV | 0 |
n | 15 |
i? | 11.12% |
PMT | 280 |
If the project has equal annual cash flows with an extra amount at the
final period, the calculation is:
PV | -2000 |
FV | 670 |
n | 8 |
i? | 10.87% |
PMT | 330 |
If the cashflows do not fit into any of the above patterns, then the
use of an NPV profile and some trial and error may be needed.
The decision criteria for IRR is to compare the project's IRR to a hurdle
rate, which should be based on the company's risk adjusted cost
of capital.
If IRR > Cost of Capital, then the project will create value if accepted.
If IRR < Cost of Capital, then value will be destroyed if the project is accepted.
For example, consider a project that has a $1,000 cost, one expected cash inflow of $1,200 at t=1 and one later inflow of -225 at t=15. The NPV Profile for the project looks like this:
This project has two IRR's -- one at 1.5% and one at 17.5%. In this situation, both are correct and neither are correct. It is best not to use IRR in this case and use just NPV instead.
MIRR provides a "fix" for some of the shortcomings of IRR
while maintaining its desirable characteristics. Its advantages are:
For example, consider Project 2:
Time | CF | FV |
1 | 1666 | 2015.86 |
2 | 334 | 367.40 |
3 | 165 | 165 |
Total FV | 2548.26 |
PV | -2000 |
FV | 2548.26 |
n | 3 |
PMT | 0 |
i? | 8.41 |
Damodaran Text Table10.11 Page 312
Technique | Primary | Secondary | ||
Number | Percent | Number | Percent | |
IRR | 288 | 49 | 70 | 15 |
ARR | 47 | 8 | 89 | 19 |
NPV | 123 | 21 | 113 | 24 |
PB | 112 | 19 | 164 | 35 |
PI | 17 | 3 | 33 | 7 |
Source: Kim, Crick, and Kim (1986) |
Technique | Rank | Relative Rank |
IRR | 1 | 1.73 |
NPV | 2 | 2.00 |
PB | 3 | 2.59 |
DPP | 4 | 3.34 |
ARR | 5 | 3.53 |
MIRR | 6 | 3.97 |
IMPORTANCE OF TECHNIQUES
BY SIZE OF RESPONDENT
Technique | Quartile 1 (Smallest) |
Quartile 2 | Quartile 3 | Quartile 4 (Largest) |
PB | 1 | 2 | 3 | 3 |
DPP | 3 | 3 | 4 | 4 |
ARR | 4 | 3 | 5 | 5 |
IRR | 2 | 1 | 2 | 2 |
MIRR | 4 | 4 | 6 | 6 |
NPV | 1 | 2 | 1 | 1 |
Incremental Analysis
After tax cash flows
Operating cash flows only
Does a change in the accept/reject decision change the cash flow in
question?
- | Price of new asset |
- | One-time costs |
+ | Sale of existing asset(s) |
+- | Tax effect on sale |
+- | Change in NWC |
- | Opportunity costs |
Net initial outlay |
Note: The sign on "CHANGE" is determined by (New - Old)
Caution: Do not include sunk costs!
+ | Change in Sales or Revenue |
- | Change in Operating Expenses |
- | Change in Depreciation |
Change in Operating Income | |
+- | Change in after-tax Income |
+ | Change in Depreciation |
- | Change in NWC in this period |
Change in Operating Cash Flow |
Note: Watch for opportunity costs, sales erosion, and allocated overhead.
Change in Operating Cash Flow | |
+- | Recovery of Net Working Capital |
+- | Change in After Tax Salvage Value |
Final Period Cash Flow |